Cleaning Aluminum Forms: Before use, clean the surface of the aluminum forms to remove dust, stains, and other impurities.

03-06 13:27

Construction process of aluminum formwork

Clean the aluminum formwork: Before use, clean the surface of the aluminum formwork to remove dust, stains, and other impurities.
Apply mold release agent: Apply a layer of mold release agent to the surface of the mold to prevent concrete adhesion.
Build the formwork: According to the design drawings and on-site dimensions, build the formwork and adjust its level and verticality.
Install the aluminum formwork: Install the aluminum formwork one by one according to the number and order, and fix it with connecting pieces.
Prepare the concrete: Prepare the concrete according to the required strength and ratio.
Pour the concrete: Pour the concrete into the formwork and consolidate it using a vibrator.
Cure the concrete: Carry out appropriate water curing according to the concrete curing requirements.
Remove the aluminum formwork: After the concrete reaches the predetermined strength, remove the aluminum formwork in the order of non-load-bearing components first, then load-bearing components.